Which of the following best describes the purpose of the Gap Analysis technique?

  • A. To allocate resources for architecture projects
  • B. To govern the architecture throughout its implementation process
  • C. To identify items omitted from the Target Architecture
  • D. To develop a set of general rules and guidelines for the architecture
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ByeWorld
3 months ago
Selected Answer: C
https://pubs.opengroup.org/togaf-standard/adm-techniques/chap05.html The technique known as gap analysis is widely used in the TOGAF Architecture Development Method (ADM) to validate an architecture that is being developed. The basic premise is to highlight a shortfall between the Baseline Architecture and the Target Architecture; that is, items that have been deliberately omitted, accidentally left out, or not yet defined.
upvoted 1 times
...
bmdibrahim
11 months, 2 weeks ago
Option C [VERIFIED] The basic premise is to highlight a shortfall between the Baseline Architecture and the Target Architecture; that is, items that have been deliberately omitted, accidentally left out, or not yet defined. https://pubs.opengroup.org/architecture/togaf91-doc/arch/chap27.html
upvoted 1 times
...
CyanideX
11 months, 3 weeks ago
Selected Answer: C
C is correct
upvoted 1 times
...
thunderks
11 months, 3 weeks ago
Selected Answer: C
Gap analysis helps in understanding the difference b/w baseline and target arch by identifying omitted or added items as per the needs refer https://pubs.opengroup.org/architecture/togaf91-doc/arch/chap27.html (figure 27-1)
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...