Question #: 28
Topic #: 1
[All TDVCL1 Questions]

What is a capability of workload management?

  • A. Prioritize memory usage for the system
  • B. Uses rules to control system performance
  • C. Provide data fabric that spans multiple systems
  • D. Determine what the SLA should be for critical work
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
lmtome44
1 year ago
B. Uses rules to control system performance. Workload management is a process of planning, scheduling, and controlling the execution of workloads on a system. The goal of workload management is to optimize the use of system resources, such as CPU, memory, and storage, in order to meet performance and service level agreement (SLA) requirements.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...