exam questions

Exam ICYB All Questions

View all questions & answers for the ICYB exam

Exam ICYB topic 1 question 3 discussion

Actual exam question from Six Sigma's ICYB
Question #: 3
Topic #: 1
[All ICYB Questions]

Training cost is $3,000 and a project required an initial investment of $12,000. If the project yields monthly savings of $1,800 beginning after 3 months, what is the payback period in months (before money costs and taxes)?

  • A. 4.17
  • B. 8.33
  • C. 11.33
  • D. 28.28
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CSCA1
3 months, 4 weeks ago
Do the math mini0616 posted below but Add 3 to 8.33 to get answer.. the key is After 3 months.. 3+8.33= 11.33 months to payoff. After 3 months it begins saving money. $15k initially invested plus 3 months of zero return plus 8.33 months of benefit equals 11.33 months to break even.
upvoted 1 times
...
mini0616
7 months, 4 weeks ago
Initial Investment: $12,000 Training Cost: $3,000 (assuming this is part of the initial investment) Monthly Savings: $1,800 (starting from the 4th month) Total initial investment = $12,000 + $3,000 = $15,000 Each month, the project saves $1,800. The payback period can be calculated as follows: Payback Period = Total Initial Investment / Monthly Savings Payback Period = $15,000 / $1,800 per month ≈ 8.33 months
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...