Question #: 32
Topic #: 1
[All CIS-ITSM Questions]

Risk is configured by default, to calculate Risk = High for a change that is scheduled with only 3 days lead time. Your customer’s change policy requires that changes be requested with 5 days lead time.
How would you satisfy this requirement?

  • A. Update the Risk Property for Insufficient lead time
  • B. Update the Risk Assessment Matrix for Insufficient lead time
  • C. Update the Calculate Risk UI Action
  • D. Update the Risk Matrix for insufficient lead time
  • E. Update the Risk Condition for Insufficient lead time
Show Suggested Answer Hide Answer
Suggested Answer: E 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Manny1218
2 months ago
IT Service Management (ITSM) Implementation On Demand Module: 7.2 Change Management Page: Understanding Risk Answer is E Change > Administration > Risk Conditions
upvoted 2 times
...
Guh
1 year ago
Selected Answer: E
Its "E" correct.
upvoted 1 times
...
153df45
1 year, 2 months ago
Selected Answer: E
It is E, tested it on PDI
upvoted 3 times
...
MarlyB
1 year, 3 months ago
Selected Answer: E
From the book: Risk is assessed based on the Risk conditions defined in Change > Administration > Risk Conditions
upvoted 3 times
...
brownbear324
1 year, 4 months ago
Selected Answer: E
CIS-ITSM ebook, pg 413
upvoted 1 times
...
armin_vcg
1 year, 4 months ago
Selected Answer: E
Problem > Change > Administration > Risk Conditions > Insufficient lead time
upvoted 3 times
...
marka_1267
1 year, 4 months ago
Selected Answer: E
E is correct, p 413
upvoted 3 times
...
Abizai
1 year, 5 months ago
Correct answer is E. Verify on instance by navigating to ALL > Change > Administration > Risk Conditions. Open "Insufficient lead time" on the list, and update the filter condition to Planned start date - relative - on o before- 5 days
upvoted 3 times
...
amineHTB
1 year, 7 months ago
Selected Answer: E
correct answer is E
upvoted 1 times
...
Amr94
1 year, 10 months ago
Selected Answer: E
Correct Ans is "E" . Update the risk condition "Insufficient lead time". We can change the filter conditions inside the risk condition- Planned start date - relative - on o before- 5 days- from now
upvoted 3 times
...
DevMoe
1 year, 10 months ago
Correct answer is E - Change ---> Risk Conditions
upvoted 1 times
...
som_420
1 year, 11 months ago
Selected Answer: E
Correct Answer : E
upvoted 1 times
...
rex11
1 year, 11 months ago
E is the answer here
upvoted 2 times
...
VVR1991
1 year, 11 months ago
Answer is E
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...