Actual exam question from ServiceNow's CIS-SPM
Question #: 10
Topic #: 1
[All CIS-SPM Questions]

Can an it_project_manager convert a task to a milestone?

  • A. No, this can only be done by a system admin.
  • B. Yes, by right-clicking on the task in the Planning Console.
  • C. No, the PPS admin role is also required.
  • D. Yes, if the task is assigned to the project manager.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
koi806
1 day, 11 hours ago
Selected Answer: B
This one shows how to do it in the planning console: https://www.servicenow.com/docs/bundle/xanadu-it-business-management/page/product/project-management/reference/r_PlanningConsoleTasks.html And this one shows that the it_project_manager role can do it: https://www.servicenow.com/docs/bundle/xanadu-it-business-management/page/product/project-management/task/t_CreateMilestones.html
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago