When defining a maintenance schedule, what type of trigger would you use for work to be performed based on time and count?

  • A. Meter and Script
  • B. Duration or Meter
  • C. Script and Duration
  • D. Duration or Script
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
GGIRARD
9 months ago
Selected Answer: B
Criteria can be duration or meter based and triggered by first occurring condition. You can update any maintenance schedule on an as needed basis. For instance, if the regular interval is due next month, you can select an earlier or later date to change when the maintenance occurs. Source : FSM ebook - (p.141)
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago