Can an it_project_manager convert a task to a milestone?

  • A. Yes, if the task is assigned to the project manager.
  • B. Yes, by right-clicking on the task in the Planning Console.
  • C. No, the PPS admin role is also required.
  • D. No, this can only be done by a system admin.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
formacion_teamnow
7 months, 2 weeks ago
Selected Answer: B
Here you can see that an it_project_manager can create a milestone: https://docs.servicenow.com/bundle/washingtondc-it-business-management/page/product/project-management/task/t_CreateMilestones.html Here you can see you can create it right-clicking on planning console: https://docs.servicenow.com/bundle/washingtondc-it-business-management/page/product/project-management/reference/r_PlanningConsoleTasks.html
upvoted 1 times
...
5da5933
10 months, 3 weeks ago
Selected Answer:
https://docs.servicenow.com/ja-JP/bundle/vancouver-it-business-management/page/product/project-management/task/t_CreateMilestones.html
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...