Why is it recommended to keep the value of the property 'com.snc.project.task.max_task_duration' to 2600 or under?

  • A. Best practices states projects should be no longer than 5 years.
  • B. The system is unable to handle more than 2600 tasks.
  • C. To avoid application memory issues.
  • D. Because projects longer than 2600 days will no longer load.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
jayhun1002
3 weeks, 5 days ago
Selected Answer: C
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/reference/r_InstalledWithProjectManagement.html
upvoted 1 times
...
1samlsof1
1 month, 3 weeks ago
C is correct Default value: 2600 Warning: Increasing the value of the property to more than 2600 will have an impact on memory usage of the platform. A very high value causes out of memory error, for example, if you try to create a project or a project task with 15000 days duration. https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/reference/r_InstalledWithProjectManagement.html
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago