Now Create provides a prescriptive methodology, leading practices, and accelerators to help with ServiceNow implementations and upgrades. How many sequential project phases and exit gates are there in the Now Create Methodology?
B is Correct.
Initiate: Understand the business objectives; establish program
governance; establish the project team; formally kick-off the project
Plan: Conduct process, platform, and integration workshops; define,
review and prioritize the product backlog; release
planning; finalize the project timeline; document the test
strategy; setup the environment
Execute: Run agile scrum cycles; define support processes and
hypercare approach; execute communications and awareness
roadshows; plan for system and user acceptance testing
Deliver: System testing and user acceptance testing; go-live
planning; operational readiness; training; go-live
Close: Operational handover; hypercare support; lessons learned;
measure value and champion success; formally close the project
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.CIS-CSM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
netvision_g
8 months, 3 weeks agoNokoNice
1 year ago