When a user's schedule changes, what action needs to be taken to update their existing data?

  • A. No action needed
  • B. Update project plans
  • C. Update calendar manually to reflect the changed capacity
  • D. Update capacity via 'Update Resource Capacity'
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
YARON_R
8 months, 3 weeks ago
Selected Answer: D
Use the Update resource capacity related link in the following scenarios: If a user is newly added and you want to update the capacity for the user. If the schedule of an existing user is changed and you want to update the capacity of the user.
upvoted 2 times
...
jptunes
9 months, 3 weeks ago
Selected Answer: D
https://docs.servicenow.com/en-US/bundle/utah-it-business-management/page/product/resource-management/task/update-resource-capacity.html
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.