The Project management application supports two types of external dependencies. What are they? (Choose two.)

  • A. Hard Dependency.
  • B. Milestone Dependency.
  • C. Soft Dependency.
  • D. Task Dependency.
  • E. Change Dependency.
Show Suggested Answer Hide Answer
Suggested Answer: AC 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
randyFarner
6 months, 1 week ago
Selected Answer: AC
From Docs: The Project management application supports two types of external dependencies - hard and soft.
upvoted 3 times
...
stophs
1 year, 6 months ago
Selected Answer: AC
a c are correct https://docs.servicenow.com/bundle/sandiego-it-business-management/page/product/project-management/concept/external-dependency-types.html
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...