Actual exam question from ServiceNow's CIS-PPM
Question #: 151
Topic #: 1
[All CIS-PPM Questions]

What must a resource plan contain if a resource plan is associated with a time card?

  • A. Soft allocation bookings.
  • B. Front load allocation spread.
  • C. Hard allocation bookings.
  • D. Even allocation spread.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
1samlsof1
3 months, 4 weeks ago
Selected Answer: C
A resource plan can be associated with a time card only if the resource plan contains hard allocations for the user. https://docs.servicenow.com/en-US/bundle/utah-it-business-management/page/product/resource-management/task/t_AssocATimeCardWithAResourcePlan.html
upvoted 1 times
...
stophs
9 months, 2 weeks ago
Selected Answer: C
c is correct https://docs.servicenow.com/en-US/bundle/utah-it-business-management/page/product/resource-management/task/t_AssocATimeCardWithAResourcePlan.html
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago