Exam CIS-PPM topic 1 question 154 discussion

Actual exam question from ServiceNow's CIS-PPM
Question #: 154
Topic #: 1
[All CIS-PPM Questions]

You can forecast future costs of projects based on (Choose two.)

  • A. Actual cost incurred
  • B. Changes in project such as project requirements
  • C. Incident cost
  • D. Paired instances
Show Suggested Answer Hide Answer
Suggested Answer: AB 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
formacion_teamnow
7 months, 2 weeks ago
Selected Answer: AB
https://docs.servicenow.com/bundle/washingtondc-it-business-management/page/product/project-management/concept/forecast-plan-for-portfolio.html As a project or portfolio manager, you can forecast the future costs of projects and portfolios based on the actual cost and changed project requirements.
upvoted 1 times
...
hkrisz79
1 year, 3 months ago
Selected Answer: AB
As a project or portfolio manager, you can forecast the future costs of projects and portfolios based on the actual cost and changed project requirements.
upvoted 1 times
...
stophs
1 year, 6 months ago
Selected Answer: AB
https://docs.servicenow.com/en-US/bundle/sandiego-it-business-management/page/product/project-management/concept/forecast-plan-for-portfolio.html
upvoted 1 times
...
stophs
1 year, 6 months ago
Selected Answer: AB
a AND b ARE CORRECT
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...