A customer needs to know what activity type is associated to time entries in the project so that they can capitalize build tasks. What is the best method to do this?
A.
Leverage project time categories to classify the time.
B.
Create a capital protect task flag.
C.
Put all capital project tasks in one phase and report from those tasks.
A time card admin or a project manager can create subcategories to define specific activities in the projects. The time card users can use these project subcategories to report time for a specific activity in a project.
https://docs.servicenow.com/en-US/bundle/utah-it-business-management/page/administer/task-table/task/create-project-time-category.html
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
tfu
1 month agojoeblogs6234
6 months, 2 weeks agostophs
9 months, 2 weeks ago