This field appears when the Rate override option is selected. If you clear the Rate override check box, the resource rate value is also cleared and removed from all calculations. On selecting the Rate override check box again, the previous resource rate is not retrieved.
https://docs.servicenow.com/bundle/utah-it-business-management/page/product/resource-management/task/t_CreateResourcePlanProjectTask.html
https://docs.servicenow.com/en-US/bundle/utah-it-business-management/page/product/resource-management/concept/c_ResourcePlans.html
If the Rate override option in a resource plan is selected, the hourly rate for calculating the corresponding resource plan cost is derived from the rate specified in the Resource rate field.
A IS CORRECT
https://docs.servicenow.com/en-US/bundle/utah-it-business-management/page/product/resource-management/task/t_CreateResourcePlanProjectTask.html
This section is not available anymore. Please use the main Exam Page.CIS-PPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
jayhun1002
4 months, 3 weeks agojayhun1002
4 months, 3 weeks agohkrisz79
8 months, 4 weeks agostophs
11 months, 2 weeks agostophs
11 months, 2 weeks ago