What is a data copy of the current project’s task, schedule, or structure that can be used for comparison reporting later?

  • A. Accrual
  • B. Forecast
  • C. Commitment
  • D. Baseline
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
netvision_g
4 months ago
Selected Answer: D
https://docs.servicenow.com/bundle/washingtondc-it-business-management/page/product/project-management/task/compare-schedule-baselines-prj.html
upvoted 1 times
...
5da5933
10 months, 3 weeks ago
Selected Answer: D
https://docs.servicenow.com/ja-JP/bundle/utah-it-business-management/page/product/project-management/task/compare-schedule-baselines-prj.html
upvoted 2 times
...
1307199725
1 year, 7 months ago
Selected Answer: D
D is correct
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...