Exam CIS-PPM topic 1 question 76 discussion

Actual exam question from ServiceNow's CIS-PPM
Question #: 76
Topic #: 1
[All CIS-PPM Questions]

If you want the project planned start date to remain the same despite the start date of the earliest task, what property would you disable?

  • A. Roll up project start date from tasks [com.snc.project.rollup_project_start_date].
  • B. Max date span into future or past from the current date for the project/project task [com.snc.project.task.check_date_span_years].
  • C. Retain start on constraint on tasks after adding relations [com.snc.project.allow_start_on_relations].
  • D. Max duration allowed for a project/project task [com.snc.project.task.max_task_duration].
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
1307199725
4 months, 2 weeks ago
Selected Answer: A
A is correct
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago