Actual exam question from ServiceNow's CIS-PPM
Question #: 74
Topic #: 1
[All CIS-PPM Questions]

Where is planned cost calculated from when requesting resources from a group and when resource role is specified?

  • A. The task rate cards.
  • B. The distribution costs.
  • C. The hourly rate of the specified role.
  • D. The CI rate cards.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
netvision_g
4 months ago
Selected Answer: C
Planned cost is rolled up from Requested Allocations for plans in the Planning or Requested state and from Resource allocations for plans in the Confirmed or Allocated state. While requesting resources from a group, if a resource role is specified, the planned cost is calculated from the hourly rate of the specified role. Source; https://docs.servicenow.com/bundle/washingtondc-it-business-management/page/product/resource-management/reference/rsrc-plan-form-tabs.html
upvoted 1 times
...
formacion_teamnow
7 months ago
Selected Answer: C
B is not what we want, we are asked about planned cost on resource request, and distribution of costs is about distributing costs among a group of records. Look for "planned cost" in the table of the article I'm linking https://docs.servicenow.com/bundle/washingtondc-it-business-management/page/product/resource-management/reference/rsrc-plan-form-tabs.html
upvoted 2 times
...
5da5933
10 months, 3 weeks ago
Selected Answer:
https://docs.servicenow.com/ja-JP/bundle/utah-it-business-management/page/product/cost-management/reference/r_UsingDistributionCostsAndRules.html
upvoted 1 times
...
1307199725
1 year, 7 months ago
Selected Answer: C
C is correct
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...