Question #: 29
Topic #: 1
[All CIS-PPM Questions]

When can a user choose from multiple rate types for their work, while logging a time card?

  • A. Only if the capability is enabled in the Project Preferences
  • B. Only if this capability is enabled in the Project Record
  • C. Only one (1) rate type can apply
  • D. Only if the capability is enabled in the Time Sheet Policies
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
[Removed]
4 months, 2 weeks ago
Selected Answer: D
https://docs.servicenow.com/bundle/washingtondc-application-development/page/administer/task-table/task/create-time-sheet-policy.html
upvoted 2 times
...
pinu_pritam
10 months, 2 weeks ago
D is correct
upvoted 1 times
...
1307199725
1 year, 4 months ago
Selected Answer: D
D is correct
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago