Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam CIS-PPM All Questions

View all questions & answers for the CIS-PPM exam

Exam CIS-PPM topic 1 question 29 discussion

Actual exam question from ServiceNow's CIS-PPM
Question #: 29
Topic #: 1
[All CIS-PPM Questions]

When can a user choose from multiple rate types for their work, while logging a time card?

  • A. Only if the capability is enabled in the Project Preferences
  • B. Only if this capability is enabled in the Project Record
  • C. Only one (1) rate type can apply
  • D. Only if the capability is enabled in the Time Sheet Policies
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
formacion_teamnow
7 months ago
Selected Answer: D
https://docs.servicenow.com/bundle/washingtondc-application-development/page/administer/task-table/task/create-time-sheet-policy.html
upvoted 2 times
...
pinu_pritam
1 year, 1 month ago
D is correct
upvoted 1 times
...
1307199725
1 year, 7 months ago
Selected Answer: D
D is correct
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...