It is here :"If a rate model is associated to the project or demand, the hourly rate is derived from the rate model. Whenever the hourly rates in the associated rate model change, you must recalculate the resource costs of the resource plan to reflect the new rates."
https://docs.servicenow.com/bundle/utah-it-business-management/page/product/resource-management/concept/c_ResourcePlans.html
If the Rate override option in a resource plan is selected, the hourly rate for calculating the corresponding resource plan cost is derived from the rate specified in the Resource rate field.
In this link itself, below is listed
"If the Rate override option in a resource plan is selected, the hourly rate for calculating the corresponding resource plan cost is derived from the rate specified in the Resource rate field."
Therefore, answer should be A i.e. Rate Override
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Guh
6 months agoa5aa8f2
8 months agoBodybuildingfly
1 year agopinu_pritam
1 year ago220052
1 year, 2 months agoD_Tech
1 year, 4 months agoLuiza25
1 year, 5 months agostophs
1 year, 6 months agoamit_arora
1 month, 2 weeks ago1307199725
1 year, 7 months ago