Exam CIS-RC topic 1 question 118 discussion

Actual exam question from ServiceNow's CIS-RC
Question #: 118
Topic #: 1
[All CIS-RC Questions]

For advanced risk assessment, risk response can be handled in the following ways:
(Choose two.)

  • A. Create multiple risk response tasks
  • B. Skipped entirely based on attributes defined in the RAM
  • C. Must create a mitigation response task
  • D. Must create at least one risk response task
Show Suggested Answer Hide Answer
Suggested Answer: AB 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
lukas98
Highly Voted 5 months ago
Selected Answer: AB
— Advanced Risk Assessment: • Mitigate, Transfer, Avoid, or Accept • Creation of a response task is optional. A comment can be entered. • Multiple response tasks can be active at a time
upvoted 7 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.