Question #: 187
Topic #: 1
[All PSM I Questions]

During the Sprint Retrospective a Scrum Team has identified several high priority process improvements. Which of the following statements is most accurate?
(Choose the best answer.)

  • A. The Scrum Team may add items to the Sprint Backlog for the next Sprint.
  • B. The Scrum Team should choose at least one high priority process improvement to place in the Product Backlog.
  • C. The Scrum Team should decline to add a process improvement to the Sprint Backlog when things are running smoothly.
  • D. The Scrum Master selects the most important process improvement and places it in the Sprint Backlog
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
e6b0f54
1 month ago
Selected Answer: A
The key is "Sprint", not Product backlog
upvoted 1 times
...
Amrx
4 months, 4 weeks ago
Selected Answer: A
The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint.
upvoted 2 times
...
DDS
9 months, 1 week ago
'A' : The Scrum Guide(2020) Sprint Retrospective - The Scrum Team identifies the most helpful changes to improve its effectiveness. The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint
upvoted 1 times
...
xcjxcj
9 months, 3 weeks ago
Selected Answer: B
Team should add to product backlog and let product owner decide the priority
upvoted 1 times
xcjxcj
9 months, 3 weeks ago
And sprint backlog created in sprint planning.(next sprint)
upvoted 1 times
...
...
UppersquareCapital
1 year, 1 month ago
Correct Answer - A
upvoted 2 times
...
Joshalom
2 years, 6 months ago
A - The Scrum Team identifies the most helpful changes to improve its effectiveness. The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint. SG2020
upvoted 3 times
...
greisymilen
3 years, 6 months ago
Should be the B. Scrum guide says: ". The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint."
upvoted 3 times
EgycrmDev
2 years, 7 months ago
Not B Only the PO can modify the product backlog
upvoted 1 times
tim_range
2 years, 6 months ago
They're modifying the Sprint Backlog, not the Product Backlog. PO owns Product Backlog, development team owns Sprint Backlog
upvoted 1 times
...
...
JohnnyP
2 years, 7 months ago
It is A based on the 2nd half of the guide "They may even be added to the Sprint Backlog for the next Sprint" - with the emphasis on "may even", which implies that this is the earliest
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...