When is the Sprint Backlog created?

  • A. At the beginning of the project.
  • B. During the Sprint Planning meeting.
  • C. Prior to the Sprint Planning meeting.
  • D. During the Sprint.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://staragile.com/blog/what-is-a-sprint-backlog-and-when-is-sprint-backlog-created

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
e6b0f54
1 month ago
D is tempting, though. "The sprint backlog is updated throughout the sprint, as more is learned". Maybe the word "Created" does the trick here?
upvoted 1 times
...
Jyoti1010
1 year, 1 month ago
Selected Answer: B
Option B
upvoted 1 times
...
Mi_Windsor
1 year, 3 months ago
B is correct
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted