Which Scrum Value is affected by a lack of trust in the Scrum Team?

  • A. Focus
  • B. Respect
  • C. Openness
  • D. Courage
  • E. Commitment
  • F. All of the above
Show Suggested Answer Hide Answer
Suggested Answer: F 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Jyoti1010
3 months, 1 week ago
Selected Answer: F
All sprint values.
upvoted 1 times
...
Mi_Windsor
5 months ago
F is the correct answer
upvoted 1 times
...
ahahahmad
2 years, 8 months ago
could anyone provide reference on this answer selected?
upvoted 1 times
negar
2 years, 8 months ago
Scrum guide 2020, Scrum Values section, page 4, the last three lines of the last paragraph
upvoted 5 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago