You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario. (Choose two.)

  • A. There should be six Product Owners, one for each Scrum Team.
  • B. There should be six Product Owners, reporting to a chief Product Owner.
  • C. The product has one Product Backlog.
  • D. Each Scrum Team should have a separate Product Backlog.
  • E. There should be only one Product Owner.
Show Suggested Answer Hide Answer
Suggested Answer: CE 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
SGN63
1 year, 1 month ago
Selected Answer: CE
The Product Owner must be the single voice of the customer, and there must be a single voice per product. https://www.scrum.org/resources/blog/can-we-have-more-one-product-owner-scrum
upvoted 1 times
...
Jyoti1010
1 year, 1 month ago
Selected Answer: CE
One product owner and one product backlog
upvoted 1 times
...
rkrau
2 years, 7 months ago
If Scrum Teams become too large, they should consider reorganizing into multiple cohesive Scrum Teams, each focused on the same product. Therefore, they should share the same Product Goal, Product Backlog, and Product Owner. --> scrum guide 2020
upvoted 1 times
...
EgycrmDev
2 years, 7 months ago
You need one Product Owner per one Product. Not more, not less https://www.linkedin.com/pulse/how-many-product-owners-do-you-need-stanislaw-matczak
upvoted 1 times
...
tomasjurkovic
3 years, 8 months ago
No, CE is correct, because there is only one product, and product owner is owner of that product, there are no 2 or multiple product owners for 1 product. So if 6 teams are working on the same product they have the same product owner.
upvoted 3 times
itzOG_
2 years, 7 months ago
I think I agree with this, its just 1 product
upvoted 1 times
...
...
7168581
3 years, 8 months ago
Why is CE not AC? Shouldn't 1 PO for 1 scrum team?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...