If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team? (Choose the best answer.)
The productivity of the original Scrum Team would likely decrease as they would need to take time to assist and support the new Scrum Teams in order for them to perform optimally.