exam questions

Exam PSM I All Questions

View all questions & answers for the PSM I exam

Exam PSM I topic 1 question 11 discussion

Actual exam question from Scrum's PSM I
Question #: 11
Topic #: 1
[All PSM I Questions]

Which of the following is required by Scrum?

  • A. Sprint Retrospective.
  • B. Members must be stand up at the Daily Scrum.
  • C. Sprint Burndown Chart.
  • D. Release planning.
  • E. All of the above.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Mordsith
Highly Voted 3 years, 8 months ago
the answer is A. because scrum framework does not have the rest as a must use.
upvoted 23 times
...
SurajKhadka
Most Recent 3 weeks, 3 days ago
Selected Answer: A
Sprint Retrospective is one of the Sprint event required in Scrum. Other options are invalid.
upvoted 1 times
...
Moise945
4 months ago
A is the correct Answer !
upvoted 1 times
...
ppons1997
4 months, 1 week ago
D is not even a thing in SCRUM
upvoted 1 times
...
Roliani
5 months, 3 weeks ago
A is the correct answer. SCRUM does not require the other options.
upvoted 1 times
...
dehbashi.project
7 months, 4 weeks ago
The true answer is " A " Actually Scrum without options B and C and D is Scrum, but without A, it's not.
upvoted 1 times
dehbashi.project
7 months, 4 weeks ago
B. The development team is enough for daily stand ups C. Dose not a requirement D. Dose not a requirement
upvoted 1 times
...
...
MarcoScaramelli
10 months, 1 week ago
A. is the correct one, others not required
upvoted 2 times
...
Djedjig
10 months, 1 week ago
A is correct
upvoted 1 times
...
mfreak
1 year ago
Selected Answer: A
I believe it's A
upvoted 2 times
...
wax_gibbous
1 year, 1 month ago
Selected Answer: A
The C and D are not even in the Scrum Guide and B is a must but the guide doesn't prescribe any such thing as standing up
upvoted 2 times
...
Micopp
1 year, 2 months ago
Selected Answer: A
Whichever tool or method is felt appropriate to measure sprint progress can be used - not necessarily burn down chart - so this invalidates suggested answer D. ....Agile Manifesto - "working software (I will insert increments for this purpose :) ) is the best measure of progress".
upvoted 1 times
...
PRINZVONBRAZILIEN
1 year, 2 months ago
The answer is A, the others is not REQUIRED, its only a plus.
upvoted 3 times
...
tinku_bowman
1 year, 2 months ago
Selected Answer: A
the others are not required
upvoted 1 times
...
Jyoti1010
1 year, 3 months ago
Sprint,Sprint planning,Daily Scrum,Sprint review and Sprint retrospective are the 5 events part of Scrum.
upvoted 1 times
...
miubaby
1 year, 3 months ago
A is the correct answer
upvoted 2 times
...
sakkal
1 year, 4 months ago
A is the answer
upvoted 3 times
...
Sayed_Aboshama
1 year, 4 months ago
The answer should be A. The other choices are not required for SCRUM
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago