Exam PSM I topic 1 question 117 discussion

Actual exam question from Scrum's PSM I
Question #: 117
Topic #: 1
[All PSM I Questions]

The Scrum Master observes the Product Owner struggling with ordering the Product Backlog. What is an appropriate action for the Scrum Master to take?

  • A. Suggest the Product Owner extend the Sprint, so he can have more time to order the Product Backlog.
  • B. Suggest that the Development Team does the ordering to be sure that it is a feasible ordering of work.
  • C. Offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize value.
  • D. Present the Product Owner with an ordered Product Backlog to use.
  • E. Encourage the Product Owner to work with the Development Team to see which items technically are fastest to implement.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Bj2
Highly Voted 2 years, 9 months ago
It should be C - the PO is owner of the product backlog and therefore the scrum master could help him to identify value therefore enable him to order by himself.
upvoted 10 times
...
correct_to_a_t
Highly Voted 2 years, 9 months ago
Dev team never orders the Product Backlog - its C
upvoted 5 times
...
dinuse123
Most Recent 1 week, 6 days ago
Selected Answer: C
Product Owner comes up with the requirement. So, Scrum master can inform him/her to provide the right backlog items.
upvoted 1 times
...
Jyoti1010
2 months, 4 weeks ago
Selected Answer: C
Correct answer is C
upvoted 1 times
...
Joshalom
1 year, 7 months ago
Correct answer is C
upvoted 1 times
...
L33roi
2 years, 9 months ago
It's C 🤓
upvoted 5 times
...
AshishJ100583
2 years, 9 months ago
I read the guide and realised it should be B. The guide says, Scrum master serves product owner in finding techniques for effective product backlog management. This easliy relates to B
upvoted 2 times
beauchamp
2 years, 7 months ago
Therefore B is not correct. as B i suggesting Dev. team, it should be PO.
upvoted 2 times
...
...
AshishJ100583
2 years, 9 months ago
I also agree, It should be C
upvoted 4 times
...
iduser
2 years, 9 months ago
why not C?
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago