Which statement is correct about the length of the Sprints?

  • A. All Sprints must be one month or less and it is optimal to have a consistent Sprint length.
  • B. The Sprint length is dependent on the development effort forecasted (amount of items selected) during Sprint Planning.
  • C. The Sprint length is calculated by aggregating the time required to design, code and test.
  • D. The Sprint Length is defined by the Scrum Master.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
amog
3 years, 8 months ago
A is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...