How much time is allowed between the conclusion of the current Sprint and the start of the next Sprint?

  • A. Maximum of one day for Sprints that are time-boxed to two weeks.
  • B. None. A new Sprint starts immediately following the conclusion of the previous Sprint.
  • C. Enough time for the last Increment to finish testing.
  • D. Enough time for the Product Owner to prepare the Product Backlog for Sprint Planning.
  • E. All of the above are allowed.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
amog
3 years, 8 months ago
B is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...