Part of the team's Definition of `Done` requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint. What should you do?
A.
Encourage the technical writers from other teams to form a specialized team to organize and plan the work for multiple teams.
B.
The Development Team members will write it as they are still responsible for creating the documentation to make the Increment done in conformance with their Definition of ג€Done.ג€
C.
Wait until the technical writer returns before continuing with related items.
D.
Complete all development work first while adding technical documentation to the Product Backlog to be done in a subsequent Sprint.
Suggested Answer:B🗳️
All Product Backlog items selected for the Sprint are owned by the Development Team as a whole. Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
amog
3 years, 8 months ago