Question #: 130
Topic #: 1
[All PSM II Questions]

How much work must a Development Team do to a Product Backlog item it selects for a Sprint?

  • A. An equal amount of time on analysis, design, programming, testing and documentation.
  • B. As much as it has informed the Product Owner will be done for every Product Backlog item it selects in conformance with the definition of ג€Doneג€.
  • C. All development work and at least some testing.
  • D. As much as it can fit into the Sprint. Any remaining work will be moved to a subsequent Sprint.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
amog
3 years, 8 months ago
B is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.