Question #: 129
Topic #: 1
[All PSM II Questions]

What should the Development Team do if they are approached by someone outside the team and asked to add a `very important` item to a Sprint that is in progress?

  • A. Add the item to the bottom of the Sprint Backlog.
  • B. Replace an item in the current Sprint of equal size.
  • C. Add the item to the top of the next Sprint Backlog.
  • D. Inform the Product Owner so he/she can work with the person.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Allow the Product Owner to decide what to do with the item as he/she is responsible for the flow of value.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
amog
3 years, 8 months ago
D is the answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.