Who is responsible for ensuring the Product Backlog items are understood to the level needed?

  • A. The Business Analyst.
  • B. The Scrum Master.
  • C. The Development Team.
  • D. The Product Owner.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
The Product Owner is accountable for managing the Product Backlog.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ferut
3 weeks, 6 days ago
I doubt between PO or Dev Team. I think it’s also not wrong to let the dev team actively query the PO until they have the confidence about their understanding. In this POV the responsibility lies on the dev team.
upvoted 1 times
...
amog
2 years, 3 months ago
D. PO is the answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago