How should a Scrum Master coordinate the work when more than one Scrum Team is working on one product?
A.
Teach them that it's their responsibility to coordinate with the other teams to integrate and create a shippable product Increment at the end of every Sprint.
B.
Identify and manage the dependencies between Scrum Teams.
C.
Have the Product Owner work with the tech leads of each team to parse the Product Backlog and minimize overlap in User Stories.
D.
Merge the teams and work from a single Sprint Backlog.