Exam PSM II topic 1 question 98 discussion

Actual exam question from Scrum's PSM II
Question #: 98
Topic #: 1
[All PSM II Questions]

If there are multiple Scrum Teams working on the same product, all of the Scrum Teams must mutually define a Definition of Ready (DoR). The DoR is a checklist that the Product Owner must fulfill before a Product Backlog item can be presented at the Sprint Planning. This protects the Development Team from interruptions and disruptions during the Sprint.

  • A. True
  • B. False
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Product Backlog items should be clear enough and have enough information for the Product Owner and Development to understand the work that needs to be done and to create a forecast of Product Backlog items to implement the Sprint Goal. Nothing stops the flow of Sprints, for example, we do not delay the Sprint because the items are not ready. In such cases, the ג€unreadyג€ items would be selected for the Sprint anyway and refined during the Sprint.
In the case that the Product Backlog items are not clear enough, the Development Team forecasts the most likely Product Backlog items to meet the goal and create a Sprint Backlog based on a likely initial design and plan. Once the time-box for the Sprint Planning meeting is over, start the Sprint and continue to analyze, decompose, and create additional functionality during the Sprint. At the end of the Sprint, the Scrum Team can discuss in the upcoming Sprint
Retrospective why this happened and what changes will make it less likely to recur.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
amog
3 years, 8 months ago
B is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.