Actual exam question from Scrum's PSM II
Question #: 96
Topic #: 1
[All PSM II Questions]

An organization is planning to form five new Scrum Teams to work on building a single product. A few of the future team members ask the Scrum Master who will coordinate the work between the different Scrum Teams.
What action should the Scrum Master take?

  • A. Visit the five Development Teams daily to ensure alignment and that all Sprint Backlogs remain synchronized.
  • B. Teach them that it is their responsibility to form the teams such that each team will have the necessary skills, knowledge, and competencies to create an integrated Increment by the end of every Sprint.
  • C. Advise the teams to minimize dependencies by working on separate development branches and integrate at the end of four Sprint cycles.
  • D. At the end of Sprint Planning, collect all Sprint tasks and create a consolidated plan for the entire Sprint.
  • E. Teach the Product Owner to work with the technical leads on ordering Product Backlog in a way to avoid too much technical and development overlap during a Sprint.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Development Teams are structured and empowered by the organization to organize and manage their own work. This includes deciding how to form teams when multiple teams are needed. The resulting synergy optimizes the Development Team's overall efficiency and effectiveness. They are self-organizing. No one (not even the Scrum Master) tells the Development Team how to turn Product Backlog into Increments of potentially releasable functionality.

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
nhungnt184
3 years, 7 months ago
Yes, B.
upvoted 1 times
...
amog
3 years, 8 months ago
B is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...