Question #: 93
Topic #: 1
[All PSM II Questions]

Which statement is FALSE in regards to the Sprint Goal?

  • A. It is only a forecast and changes during the Sprint as more is learned.
  • B. If it doesn't seem achievable, the Development Team has the courage to tell the Product Owner.
  • C. The Product Owner respects the Development Team's opinion on whether they can achieve it.
  • D. It helps increase focus.
  • E. The Scrum Team discusses openly about alternative ways to reach it.
  • F. The Development Team commits to it.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
The Sprint Goal is an objective set for the Sprint that can be met through the implementation of Product Backlog. It provides guidance to the Development Team on why it is building the Increment.

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
nhungnt184
3 years, 7 months ago
A. The Sprint Goal does not change during the Sprint.
upvoted 1 times
...
amog
3 years, 8 months ago
A is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted