Exam PSM II topic 1 question 81 discussion

Actual exam question from Scrum's PSM II
Question #: 81
Topic #: 1
[All PSM II Questions]

In what ways does the Scrum Master keep a Development Team working at its highest level of productivity?

  • A. By removing impediments that hinder the Development Team and facilitating Development Team decisions.
  • B. By helping the Development Team with user acceptance tests and tracking defects.
  • C. By ensuring each member takes turns speaking at the Daily Scrum and ending the event on time.
  • D. By keeping the Scrum board and burn-down chart updated daily.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
The Scrum Master serves the Development Team by removing impediments to the Development Team's progress and facilitating Scrum events as requested or needed.

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
nhungnt184
3 years, 7 months ago
A is correct.
upvoted 1 times
...
amog
3 years, 8 months ago
Answer is A
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...