Adding more resources in Scrum will proportionally increase the value delivered.

  • A. True
  • B. False
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
When working on complex problems in complex environments, adding more resources (people, money, tools, etc.) cannot guarantee increased value or success.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
amog
3 years, 8 months ago
B: False
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...