A Scrum Team has been working on the same product for twelve Sprints. What would likely be the immediate impact on the original Scrum Team if two new Scrum Teams are to be added the same product?
Suggested Answer:A🗳️
The productivity of the original Scrum Team would likely decrease as they would need to take time to assist and support the new Scrum Teams in order for them to perform optimally.
I wish there will be no vague questions like this in the exam. Productivity will be decreased in the short term but might be increased in the long term due to the support from other teams