Which two scenarios would best represent a self-organizing Development Team? (Choose two.)
A.
The Development Team members are strictly focused on the work within their functional role and always handing off the work to other roles in a timely matter.
B.
Management works with the Scrum Master to optimize the Development Team's progress during the Sprint.
C.
Development Team members collaboratively select and re-plan their work throughout the Sprint.
D.
The Development Team invites external people to the Sprint Planning to help them create a complete and detailed Sprint Backlog.
E.
The Development Team creates its own Sprint Backlog, reflecting all work that is part of the Definition of Done.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Mbouzidi
4 months agoMi_Windsor
1 year, 3 months agocsmvv
1 year, 3 months agoamog
3 years, 8 months ago