Which two scenarios would best represent a self-organizing Development Team? (Choose two.)
A.
The Development Team members are strictly focused on the work within their functional role and always handing off the work to other roles in a timely matter.
B.
Management works with the Scrum Master to optimize the Development Team's progress during the Sprint.
C.
Development Team members collaboratively select and re-plan their work throughout the Sprint.
D.
The Development Team invites external people to the Sprint Planning to help them create a complete and detailed Sprint Backlog.
E.
The Development Team creates its own Sprint Backlog, reflecting all work that is part of the Definition of Done.
This section is not available anymore. Please use the main Exam Page.PSM II Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Mbouzidi
9 months agoMi_Windsor
1 year, 8 months agocsmvv
1 year, 8 months agoamog
4 years, 1 month ago