Actual exam question from Scrum's PSM II
Question #: 36
Topic #: 1
[All PSM II Questions]

Individual Development Team members have been approaching Steven, the Scrum Master, to complain about Chris. Chris has the most experience on the system they are building. He often questions the choices team members make in design and architecture making them feel bad.
What are two good ways for Steven to address this problem? (Choose two.)

  • A. Steven observes whether this topic is raised at the Sprint Retrospective. If not, then he checks with the team on how comfortable they are with the way the design and architecture is being handled.
  • B. Steven suggests facilitating a session with the full team to help resolve the issue.
  • C. Steven tells the concerned members that Chris' opinions should be respected as he has the most experience and understands what is best for long term sustainability.
  • D. Steven shares his concerns with Chris and the impact on the other team members and that he should be a team player.
  • E. Steven takes the time between Sprints to organize a team building session to build a stronger relationship.
Show Suggested Answer Hide Answer
Suggested Answer: AB 🗳️
Conflicts are a natural occurrence and the Scrum Master coaches the Development Team on the value of resolving conflicts. Leaving conflicts unresolved can impact the Scrum values of openness and respect diminishing trust. Lower trust levels will impact the Scrum Team's effectiveness and can cause impediments in the future. It is the responsibility of the Scrum Master to remove impediments that hinder the team through conflict resolution and facilitation.

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Mbouzidi
4 months ago
Selected Answer: AB
A B souhld be the best ways to resolve issue
upvoted 1 times
...
OMG4567
4 months, 1 week ago
Selected Answer: AB
This is a topic for the Retro. It is best to involve the whole Scrum team into the solution of a conflict. Furthermore everybody might be coached to WoW in Scrum in another session outside of the scrum meetings since the SM is responsible everybody understood the Scrum rules.
upvoted 1 times
...
Ameet9
7 months, 1 week ago
Selected Answer: BD
shouldn't it be B and D
upvoted 1 times
...
LuckyAro
10 months ago
Selected Answer: AD
SM can not facilitate another session outside of scrum meetings as that is not within the scrum requirements. Discussing 1-1 with the member to teach scrum values is more reasonable than going outside the rules of SCRUM.
upvoted 1 times
...
Mi_Windsor
1 year, 4 months ago
A and B are correct
upvoted 1 times
...
lenanguyen89
1 year, 5 months ago
Should be A & B I think
upvoted 2 times
...
DRSyourGME
1 year, 6 months ago
Question# 35 is similar. Why has #36 two correct answers and #35 only one?
upvoted 1 times
...
amog
3 years, 8 months ago
Conflict should be resolved with the involved of all persons relate. Can't ask one side deal with problem for other one's happiness Should be A and B
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...