Steven, the Scrum Master, observes that one of the Development Team members is not attending the Daily Scrum. The Development Team feels this is ok as they all sit in the same area and already have constant communication throughout the day.
Which is the best action for Steven to take?
Mbouzidi
4 months agoMi_Windsor
6 months, 1 week agoamog
3 years, 8 months ago