During Sprint Planning, the Definition of Done will help the Development Team forecast the amount of work, selected from the Product Backlog, deemed feasible to make 'done' by the end of the Sprint.
Which two items best describes what 'done' means? (Choose two.)

  • A. All the work needed to prepare the Increment for User Acceptance Testing.
  • B. All the work needed to prepare the Increment for Integration Testing.
  • C. Having an Increment of working software that is potentially releasable to the end users.
  • D. All the work performed as defined in the Definition of Done.
  • E. All the work completed within the current skills and expertise in the Development Team.
Show Suggested Answer Hide Answer
Suggested Answer: CD 🗳️
When a Product Backlog item or an Increment is described as 'Done', everyone must understand what 'Done' means. Although this may vary significantly per
Scrum Team, members must have a shared understanding of what it means for work to be complete, to ensure transparency. This is the Definition of Done for the
Scrum Team and is used to assess when work is complete on the product Increment. The purpose of each Sprint is to deliver Increments of potentially releasable functionality that adhere to the Scrum Team's current Definition of Done.

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Mbouzidi
4 months ago
Selected Answer: CD
C D are correct
upvoted 1 times
...
Mi_Windsor
1 year, 4 months ago
C and D
upvoted 3 times
...
abenmariem
1 year, 6 months ago
why E isn't correct ?
upvoted 1 times
...
haminh
2 years, 7 months ago
C is no longer valid! The term “potentially releasable” no longer used to describe the Increment. The Scrum Team should work on and deliver a product increment which usable and valuable at the end of every Sprint.
upvoted 3 times
...
amog
3 years, 8 months ago
C and D are correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...