Question #: 29
Topic #: 1
[All PSM II Questions]

Peter, a Project Manager, has raised concerns about your Scrum Team's productivity and progress towards the objectives.
Which is the best way to respond to Peter's concerns?

  • A. Share the Product Backlog, the projections towards the release dates and ensure that Peter has access.
  • B. Show the Profit & Loss (P&L) report.
  • C. Share the current impediments.
  • D. Share the last stakeholder status report prepared by the Scrum Master.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
One of the key pillars that support the empirical process control is Transparency. Transparency will help manage stakeholder expectations and allow the teams to effectively adapt if and when needed.

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Mbouzidi
4 months ago
Selected Answer: A
A is correct
upvoted 1 times
...
Mi_Windsor
1 year, 4 months ago
A is the correct answer
upvoted 1 times
...
nhungnt184
3 years, 7 months ago
Why not C?
upvoted 3 times
stealthelephant
1 year ago
Because the developers are responsible for managing sprint impediments and in the review they will cover their progress.
upvoted 1 times
...
...
amog
3 years, 8 months ago
Should be A
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...