In order to start the first Sprint, Scrum only requires a Product Owner with enough ideas, a Development Team to execute on those ideas, and a Scrum Master to guide the process.
It's hard to say true or false. It depends on how the person worded the question assuming the PO has transformed his ideas on product backlog with product goal or not.
In case yes then the response is true. Otherwise the response is false.
This is one of those that sound good when you read it but in Scrum Guide it is explicitly stated that you need formulated Sprint Goal which is formulated by PO and Sprint Backlog formulated during Sprint Planning. Also how can you start work when there are no Produt Backlog Items in Product Backlog created?
To start the first Sprint, the Product Backlog should have enough items selected and appropriately ordered by the Product Owner to form a Sprint Goal and a potentially releasable Increment. The Sprint Goal defines the objective for the Sprint, and the Increment is the sum of all the completed Product Backlog items at the end of the Sprint.
So, while having a Product Owner, Development Team, and Scrum Master is necessary, the presence of a well-prepared Product Backlog is also required to begin the first Sprint in Scrum.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Mbouzidi
4 months agoMbouzidi
4 months agoMi_Windsor
6 months, 1 week agoKarkos
1 year, 1 month agoKarkos
1 year, 1 month ago572f16d
1 year, 5 months agolenanguyen89
1 year, 6 months agoamog
3 years, 8 months ago