exam questions

Exam PSM II All Questions

View all questions & answers for the PSM II exam

Exam PSM II topic 1 question 24 discussion

Actual exam question from Scrum's PSM II
Question #: 24
Topic #: 1
[All PSM II Questions]

In order to start the first Sprint, Scrum only requires a Product Owner with enough ideas, a Development Team to execute on those ideas, and a Scrum Master to guide the process.

  • A. True
  • B. False
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
SurajKhadka
1 month ago
Selected Answer: B
Having "ideas" is not the same as having a properly ordered Product Backlog
upvoted 1 times
...
Mbouzidi
5 months ago
Selected Answer: A
A is the correct The response is True as the ideas form the goal.
upvoted 1 times
...
Mbouzidi
5 months ago
It's hard to say true or false. It depends on how the person worded the question assuming the PO has transformed his ideas on product backlog with product goal or not. In case yes then the response is true. Otherwise the response is false.
upvoted 1 times
...
Mi_Windsor
7 months, 2 weeks ago
A is my answer
upvoted 1 times
...
Karkos
1 year, 2 months ago
Selected Answer: B
This is one of those that sound good when you read it but in Scrum Guide it is explicitly stated that you need formulated Sprint Goal which is formulated by PO and Sprint Backlog formulated during Sprint Planning. Also how can you start work when there are no Produt Backlog Items in Product Backlog created?
upvoted 2 times
Karkos
1 year, 2 months ago
Also - how can you begin on creating potentially shippable Increment without Definition of Done?
upvoted 1 times
...
...
572f16d
1 year, 6 months ago
Selected Answer: B
To start the first Sprint, the Product Backlog should have enough items selected and appropriately ordered by the Product Owner to form a Sprint Goal and a potentially releasable Increment. The Sprint Goal defines the objective for the Sprint, and the Increment is the sum of all the completed Product Backlog items at the end of the Sprint. So, while having a Product Owner, Development Team, and Scrum Master is necessary, the presence of a well-prepared Product Backlog is also required to begin the first Sprint in Scrum.
upvoted 2 times
...
lenanguyen89
1 year, 7 months ago
A is correct
upvoted 1 times
...
amog
3 years, 9 months ago
A is the answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago