Question #: 21
Topic #: 1
[All PSM II Questions]

What is management's role in Scrum?

  • A. To provide the necessary environment and support needed as defined by the Scrum Guide by providing insights and resources that help the Scrum Teams continue moving forward.
  • B. Identifying and removing people that are performing poorly.
  • C. Monitoring skill levels of the Development Team.
  • D. Monitoring the Development Team's velocity.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Getting the support from the business side helps facilitate the changes that fosters empiricism, self-organization, bottom-up intelligence, and intelligent release of software.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Mbouzidi
5 months ago
Selected Answer: A
A is correct
upvoted 1 times
...
Mi_Windsor
7 months, 2 weeks ago
A is correct
upvoted 1 times
...
lenanguyen89
1 year, 7 months ago
A is correct
upvoted 2 times
...
amog
3 years, 9 months ago
A is the answer
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago