A Scrum Team has requested a hardening Sprint to integrate the work produced in previous Sprints and test before releasing. What three scenarios has likely occurred? (Choose three.)
A.
The team's Definition of Done is not being adhered to during every Sprint.
B.
The team's Definition of Done is weak or incomplete causing a build up of technical debt.
C.
The Development Team is having difficulties with the ability to regularly release during a Sprint.
D.
Hardening Sprints are supported by the Scrum framework so this is acceptable.
E.
Scrum has been customized in a suitable manner to make the previous work releasable.
Suggested Answer:ABC🗳️
At the end of a Sprint, the new Increment must be 'Done', which means it must be in useable condition and meet the Scrum Team's Definition of Done.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Mbouzidi
4 months agoMi_Windsor
1 year, 4 months agolenanguyen89
1 year, 6 months agoamog
3 years, 8 months ago