Exam PSM II topic 1 question 9 discussion

Actual exam question from Scrum's PSM II
Question #: 9
Topic #: 1
[All PSM II Questions]

A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)

  • A. Impediments are raised and resolved more slowly.
  • B. Opportunities to inspect and adapt the Sprint Backlog are reduced.
  • C. Less information about the progress will be shared causing the Sprint plan to become inaccurate and reducing transparency over progress toward the Sprint Goal.
  • D. The Scrum Master loses the ability to update the burndown chart adequately.
  • E. The Product Owner cannot accurately inspect utilization of the individual team members.
Show Suggested Answer Hide Answer
Suggested Answer: ABC 🗳️
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint Goal. Every day, the
Development Team should understand how it intends to work together as a self-organizing team to accomplish the Sprint Goal and create the anticipated
Increment by the end of the Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Mbouzidi
5 months ago
Selected Answer: ABC
A B C are correct
upvoted 1 times
...
Mi_Windsor
7 months, 2 weeks ago
ABC are correct
upvoted 1 times
...
MYAT_T0T
9 months ago
A, B and C are correct.
upvoted 1 times
...
lenanguyen89
1 year, 7 months ago
A B C I think.
upvoted 1 times
...
nhungnt184
3 years, 8 months ago
A, B and C.
upvoted 1 times
...
amog
3 years, 9 months ago
A, B, C are correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago